Public data on the environmental footprint of data centers: air sensor readings, noise measurements, water use, electricity use and carbon dioxide estimates, and updates on legal, regulatory and scientific developments.
For now, this page focuses only on the Potomac basin for a couple of reasons. Data center water usage impacts are by their nature local and depend on the local river, aquifer and utility. The Potomac River basin in Northern Virginia (Loudoun, Prince William and Fairfax counties) has the largest concentration of data centers in the world, and the Potomac is the main drinking water source for the Washington metropolitan area. Also, it is the only place we found with a public, basin-wide estimate of data center water usage, contained in a March 2026 report by the Interstate Commission on the Potomac River Basin (ICPRB).
Other regions will be added if we locate comparable data.
Potomac basin, 2025, in million gallons per day (MGD), rounded. Consumptive use is water withdrawn and not returned to the river or sewer system. These are ICPRB projections for 2025, modeled from trends in water use reported by the basin states from 2003 to 2020, not measured 2025 values. Consumptive use is estimated by multiplying withdrawals by a fixed factor for each sector. (ICPRB, Potomac Basin Trends in Reported Water Use, March 2024, Table 3.)
| Sector | Withdrawals (MGD) | Consumptive use (MGD) |
|---|---|---|
| Thermoelectric power | 2,099 | 42 |
| Hydroelectric | 1,222 | 0 |
| Public water supply | 676 | 68 |
| Other (use not identified) | 89 | 89 |
| Mining | 53 | 5 |
| Aquaculture | 28 | 1 |
| Irrigation | 23 | 21 |
| Industrial | 22 | 3 |
| Commercial | 9 | 5 |
| Livestock and self-supplied domestic | under 1 | under 1 |
| All sectors | 4,221 | 234 |
"Other" is reported withdrawals whose use could not be identified. ICPRB assumes all of it is consumed and projects it falling to near zero by 2050, which is why the basin's projected consumptive use drops from about 234 MGD in 2025 to about 164 MGD in 2050. ICPRB's sectors do not include data centers as their own category; data centers served by public utilities fall within public water supply.
| Area | 2025 average consumptive use (MGD) | 2025 peak day (MGD) | Share of area total | 2050 average (MGD) | 2050 peak (MGD) |
|---|---|---|---|---|---|
| Washington metropolitan area | about 4 | about 15 | 1% of withdrawals; 9% of consumptive use (up to 12% in summer) | about 22 | over 80 |
| Upstream of the metropolitan area intakes | under 0.1 | about 0.3 | not reported | about 5 | about 17 |
2050 values are ICPRB projections based on load forecasts from PJM Interconnection (PJM, the regional grid operator whose territory includes Virginia) and low, medium and high cooling scenarios. In summer, monthly data center use can reach nearly three times the annual average, when river flows are lowest.
No measured study linking data center water use to a change in drinking water quality was found.
| Topic | What has been reported |
|---|---|
| Low river flow | ICPRB states that summer data center demand coincides with the lowest river flows and that reduced streamflow could concentrate discharged contaminants. It presents no measured low-flow or water quality analysis. |
| Discharges | ICPRB reports that most regional data centers discharge to municipal sewers. Direct discharges could raise temperature, salinity, minerals and other contaminants, which ICPRB says may need further study. |
| Groundwater supply, Virginia | A Virginia Department of Environmental Quality (DEQ) study of groundwater east of Interstate 95 (I-95), roughly the Virginia Coastal Plain, finds the supply constrained, with declining availability projected (Key Points). It reports no publicly available comprehensive data on how much data center water comes from groundwater, and that most existing and planned data center capacity statewide is in public water supply areas that draw mainly on surface water (page 66). None of DEQ's simulated large withdrawals met the criteria for a groundwater permit, and DEQ concludes a data center with evaporative cooling is unlikely to find a reliable groundwater supply anywhere in the Coastal Plain (page 69). (Virginia DEQ, July 2026) |